Hospital Metropolitano: renovation of 38 bathrooms

Removal of fixtures, demolition of 1,468.80 m² of wall tiling and 219.60 m² of flooring, and 798 m² of substrate levelling. New ceramic wall tiling and 171 m² of floor tiles, skirting, thresholds, granite vanities with basins and granite partitions, materials and labour included.

Client
Hospital Metropolitano (Grupo Kora Saúde)
Location
Civit II, Serra
Dates
Sep 2021
Status
Completed
Quantities and quality control
ItemUnitQuantity
Bathrooms renovatedund38
Ceramic wall cladding, laid (including grout)m²922.26
Substrate leveling for cladding (3 cm)m²798
Ceramic floor tiling, laidm²171
Ceramic wall cladding demolitionm²1,468.80
Ceramic floor tile demolitionm²219.60
White Itaúnas baseboard 10 cmm248.52
Granite partitions 0.60x1.80und38

Source: the project's progress reports.